Thursday, January 14, 2021

Thursday


Here are some shots of #15.  Below, you can see we covered the slope with a straw matting material to prevent any erosion potential.  We have 2 loads of sod coming next week that will cover the slope.





Below, at the croquet lawn, excvation work continues. Excess soil from this site is being hauled to #11, where a drainage projet will soon begin and involves raising up a portion of the fairway.







Above, the yellow line shows the position of the new lawn and how it will be oriented on the site.


On #9, we installed about 13 pallets of sod that were stored inside la`st night to thaw out.  The remainder of the sod was placed inside for the evening which will hopefully allow us to lay it tomorrow.