Tuesday, August 11, 2026

Tuesday

 

Cross is out in full force, mowing out of play areas with our brush mower.  This is something we're making more of an effort with this year.  It definitely provides a slightly cleaner look.


You'll see a lot of action taking place today around the dam and the irrigation pumphouse.  We are digging a 36" deep ditch to bury an electric line underground, that services the pumpstation.  This is in preparation for the dam project, scheduled to start in November.  In order to reconstruct the abutment walls on the dam, we must move the current power poles that service the pumpstation, overhead.  Those power poles are in the vicinity of where the new walls will be located.