Steps at #10 Tee


Now that a majority of the rough grading is complete around the 10th tee, this will start to come together nicely.  We started on the the rock steps that lead to the Jones Tee.  Remember, this whole area dropped 24" giving the feel that the Jones Tee is now elevated.  I'll show photos later today of the rock wall that will also go along the tee and tie into these steps.  

We also received the engineered drawings for the 6" water line and will hopefully be installing that during the next 2 weeks.  Once that is complete, we'll be able to finally get some sod.  On February 11th, a contractor will be here to laser level the new Men's tee on this hole.