Friday, September 29, 2017

Paving Update:

Below is an email to POA general manager, Dan Marshall from the outfit (Harrison Construction) doing the paving work on state owned roads around the Club:
 
Dan,
 
Just thought I would update you on the latest paving schedule. Harrison Construction has indicated that they intend to move a crew to Highlands on October 2 2017 to begin patching operations. They are going to start that day on Poplar St. and if all goes well they will probably move to Cobb Rd on the 3rd.. We will try to keep you updated as closely as possible. The patching operation will consist of moving from one patch location to the next and I would anticipate that when the Cobb Rd patching is complete they will move to either Moorewood Rd or Hudson Rd. Another crew will come on site at a later date to do the resurfacing operation. Expect a lot of noise and large construction equipment. Gregg Wallace (Assistant Resident Engineer) or myself will keep you notified as work progresses. 
 
Thanks, Shawn