It is a wet, nasty Monday but we can't afford to stop regardless of the Holiday! Sand installation and bunker shaping and sodding continues.
Below, my concrete man poured all of the footers today that will support the new walls at the croquet court. Hopefully, wall forms will be installed as early as next week. Once the forms are removed, we will need to wait about 3 weeks until backfilling and stone work is allowed.