Monday at HCC

It is a busy day at HCC!  Our goal is to complete the rock wall on the nursery lot besides the GM house.  Some of the staff is out stripping sod and in the mean time:

1. I met with the rock mason who is starting on the new pillars in hwy 106 next Monday.
2. We dug the footers for the new bridge on #10.  The footers will be formed tomorrow and poured on Wednesday.
3. Trees were delivered for the new landcape screening below the Security building.
4. Our new aeration system was installed in the pond on #1 to help the trout through the summer heat.
5. Course Crafters is on site and situated and started work on the 11th green.