Thursday, December 09, 2021

Thursday Updates

Above, you can see the contractor is working their way down the 10th hole, installing a new irrigation main line.  Right now, it remains a slow process because we are having to dodge a lot of old and new water lines, sewer lines, fiber optic lines and power lines that run to the Hudson House. Below, the overhead view of #15 pond and the current status of dredging.

These next 2 photos give you a better idea of the new approach contours on #15.  The white line is the approximate edge of the new approach.



Finally, on #8, we removed all of the sod from around the green to get ready for some major drainage enhancements that are coming soon.  Not only are we resizing the culvert under the approach, but we are adding additional internal drainage all around the green.  A large drain pipe at the base of the slope will capture seepage drainage that constantly leaks from the base of the hill.