Wednesday, May 20, 2026
The Future of Golf Course Mowing
Highlands CC Dam Work
The valve replacement at the dam will start next Tuesday, after Memorial Day. This week, we are working to calibrate the siphon, to be comfortable how much we are drawing the lake level down. We are currently about 1 foot below dam level and that shouldn't change. In fact, if we get the rain that is predicted later this week, we will more than likely be filled back to capacity. Here is a sneak peak at my upcoming Piper article. I've decided to share this now because I feel it's timely and want you to be aware of what were are working on as you see the equipment an action in the area...
There are so
many dam projects taking place at Highlands CC.
And as your Golf Course Superintendent, I have the responsibility of
being the dam project manager for said projects, with the help of Greg
Crawford, of course. Ok, ok… of course I
am not swearing. I’m simply referring to
the dam on Club Lake, at the corner of Dillard Road and Hudson Road. For those who know me, know I will never- and
have never- passed up the opportunity to inject sophomoric humor in a
conversation (or newsletter in this case); especially dam humor, when used in
the appropriate context…or inappropriate, maybe. I don’t know…
Regardless, there is a lot going on and I’d like to tell you about these
projects!
The dam has been separated into two phases. Both phases are permitted through the NCDEQ (NC Dept of Environmental Quality) and NC Dam Safety. We engaged an engineering firm in Asheville several years ago to perform the design work and then hired North Georgia Concrete to perform the actual work. The first phase, which was completed in May of this year, involved the replacement of the drain valve in the dam. This phase was required because our existing valve failed, which meant we had no way of draining the lake in the event of a very unlikely emergency. This work was relatively straightforward. We lowered the lake level a few feet using a series of siphon pipes. Once the water was down a few feet and not flowing over the top of the dam, it allowed us to create a dry space to work. A new valve was installed on the downstream side of the dam and cased in concrete. Once the valve was installed, a team of divers, who specialize in this work, dove down to the bottom of the dam (about 13ft-15ft) and removed the components of the old valve system. For the most part, the work was noninvasive and easy to clean up. The reason this project occurred during the season was because of the dredging project behind the LEC. We could not lower the lake level without impacting the dredging operation that occurred all winter. The dredging project took priority, and we completed phase one of the dam work once the dredging concluded on May 16th. Ideally, we hoped to complete this work during the winter. Phase one was quick, only lasting about five days of actual work.
Now enter phase two, which will begin in November or December of 2026. This phase is a much more involved project, and it is a much larger project. First, we are required by the NCDEQ to remove four trees growing alongside the dam. The root system of these trees has played a small role in some of the minor issues we are seeing. Again, most of the issues which are relatively minor are caused by aging concrete. Keep in mind, the existing dam was constructed in the early 1930’s! Phase two will require the lake to be fully drained. The winter of 2026/2027 will be a great time to see how many golf balls line the bottom of the lake! During this phase, which will last as long as two or three months, we will be rebuilding the abutment walls on both sides of the dam. This will involve a fair amount of heavy equipment and the general look of the dam, when complete, will be slightly different.
Now, here is some background information that I believe you’d be interested in:
If you’ve been around Highlands Country Club for 17 years or more, you might be asking yourself: “Didn’t we rebuild the dam during the winter of 2009?” The answer to that question is “sort of.” In 2009, we did work on the dam, but only on the spillway. Using jack hammers, a contractor chipped away approximately 6” of the spillway surface and then poured new concrete on the face of the spillway. At that time, we did not address the abutments, because they were not an issue. The spillway work is doing great and will not be affected nor included in any of this work, during phase two.
Your next question might be, “How did this all come about and why is the Club focused on this now?” That’s a great question! The State of NC has an entire Dam Safety Division. These folks inventory all the dams in the State and periodically inspect them. During the inspection process, they drill core samples in dam components and send them to a lab for testing. If the dam doesn’t meet the NC standard for concrete strength and durability, the owner of the dam receives a letter that outlines what specifically needs to be addressed. When the Club received this letter approximately two years ago, we engaged the help of an engineering firm and ultimately a contractor. You’ll also be interested to know that every year, in February, Highlands CC submits an Emergency Action Plan to the State of NC, that outlines the steps to be taken in the unlikely event of a dam breach. This document is about 20 pages long and consists of topographical and GPS maps. Working with our engineers, we developed the EAP several years ago and update it annually.
Monday, May 18, 2026
Dam Project
Friday, May 15, 2026
Wednesday, May 13, 2026
Tuesday, May 12, 2026
The Farm
Monday, May 11, 2026
Monday
Friday, May 08, 2026
Take-All Patch
Thursday, May 07, 2026
Fallen Tree
Rain Totals Update
Over the past 24 hours, we received a much needed 2.4" of rain!
However, we remain 15" below normal for this time of year. If the season continued like it is now, we would receive the equivalent of 51" of rain for the year. Our average is about 92"/year.
Wednesday, May 06, 2026
Wednesday
John Branson, our dedicated Landscape Technician, is doing a phenomenal job refreshing the courtyard gardens. He is working with Mary Palmer Dargan to make this year the best yet, for the courtyard. I'm so proud of the level of passion and ownership he has taken on this project. John just celebrated his 26th birthday and he is wise beyond his years! Highlands CC is fortunate to have him leading the landscape charge!
Monday, May 04, 2026
Monday
Friday, May 01, 2026
Greens Update
Yesterday afternoon, we began light verticutting of putting greens on the golf course. We also started double cutting, but that won't become routine until we receive our seasonal staff later in May. In fact, it looks as if we'll have boots on the ground by May 18th. Labor has been a huge challenge with all the golf courses in the Highlands/Cashiers area. The greens are rolling 10'6" this morning and that stimpmeter reading will increase as the days progress and warmer temperature become more consistent. Regardless, I am very happy with where we are right now.





























