Sod is being installed by Team HCC around the 10th tee box.

The 9th tee box is complete and awaiting Bentgrass sod.  Lowering the retaining wall on the steps, allowed us to make the tee a foot wider and perfectly rectangular.





Our new stand-alone forward tees are being constructed.  Many, like #8 below, are built in front of the fairway or off to the side.  On #6, pictured above, Ron Forse liked the location so much that we are keeping the same tee, but modified the border of the fairway so the tee sits in rough, not in the fairway like last season.



Work on the #15 green cart path continues.  The remaining grass in the area was removed and now fill is being hauled in to allow us to shape the area, visually hiding a lot of the cart path.